After successful on-grid power generation on February 1,2019,Four turbine-generating unit of Wucheng shipping Yangbu power station completed 72-hours trial operation from February 8 to February 24’ 16 o’clock,operation condition is good and various indexs comply with technical specification.
The Qujiang Shipping Development Project is an important infrastructure for Zhejiang's “Port Trade and Shipping Strong Province”,which is mainly base on shipping and generation,is a pivotal project that combines with improvement of water environment and irrigation,The Youbu hub project for power generation is the fifth-level hub in the six-level development of the mainstream of the Qujiang River.It was built in September 2014. The power station has a total of four hydroelectric generating units with a total installed capacity of 16 MW. The designed annual generating capacity is 647,50 MWh, which is the largest hydropower station with the largest installed capacity in Jinhua City.




|